Concrete pouring , section 07 level 1 slab underground parking plaza Post author:Admin Post published:September 30, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingConcrete pouring , section 07 level 1 slab underground parking plaza
Concrete pouring , section 03 level 1 slab underground parking plaza Post author:Admin Post published:September 28, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingConcrete pouring , section 03 level 1 slab underground parking plaza
Reinforcement is in final level for concrete pouring , section 07 level 1 slab underground parking plaza Post author:Admin Post published:September 27, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingReinforcement is in final level for concrete pouring , section 07 level 1 slab underground parking plaza
Utilities shifting ( partial portion) due to sewer line and storm water drain alignment is underway Post author:Admin Post published:September 25, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingUtilities shifting ( partial portion) due to sewer line and storm water drain alignment is underway
Epoxy base paint work and MEP works ( Electrical Cable trays , Fire suppression system and under other conduit works) are underway at underground parking plaza Post author:Admin Post published:September 24, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingEpoxy base paint work and MEP works ( Electrical Cable trays , Fire suppression system and under other conduit works) are underway at underground parking plaza
Concrete of section 03 (partial) is poured and reinforcement of section 07 ( partial) is under preparation Post author:Admin Post published:September 23, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingConcrete of section 03 (partial) is poured and reinforcement of section 07 ( partial) is under preparation
Stone Soling and Lean Concrete base is under way at section 08 underground parking plaza Post author:Admin Post published:September 21, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingStone Soling and Lean Concrete base is under way at section 08 underground parking plaza
Scaffolding for water tank Slab preparation is under way at underground parking plaza Post author:Admin Post published:September 20, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingScaffolding for water tank Slab preparation is under way at underground parking plaza
Subbase preparation is underway at Deen M Wafai Road Post author:Admin Post published:September 19, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingSubbase preparation is underway at Deen M Wafai Road
Stone ballast layer compaction is in process at Deen Mohammad Wafai Road ( 100-meter Stretch) Post author:Admin Post published:September 18, 2019 Post category:Progress Updates Post comments:0 Comments Continue ReadingStone ballast layer compaction is in process at Deen Mohammad Wafai Road ( 100-meter Stretch)