Concrete pouring , section 07 level 1 slab underground parking plaza
Continue Reading
Concrete pouring , section 03 level 1 slab underground parking plaza
Continue Reading
Reinforcement is in final level for concrete pouring , section 07 level 1 slab underground parking plaza
Continue Reading
Utilities shifting ( partial portion) due to sewer line and storm water drain alignment is underway
Continue Reading
Epoxy base paint work and MEP works ( Electrical Cable trays , Fire suppression system and under other conduit works) are underway at underground parking plaza
Continue Reading
Concrete of section 03 (partial) is poured and reinforcement of section 07 ( partial) is under preparation
Continue Reading
Stone Soling and Lean Concrete base is under way at section 08 underground parking plaza
Continue Reading
Scaffolding for water tank Slab preparation is under way at underground parking plaza
Continue Reading
Subbase preparation is underway at Deen M Wafai Road
Continue Reading
Stone ballast layer compaction is in process at Deen Mohammad Wafai Road ( 100-meter Stretch)