Skip to content

Karachi Neighborhood Improvement Project

ENGLISH   |   URDU   |   SINDHI

Karachi Neighborhood Improvement Project

ENGLISH   |   URDU   |   SINDHI

Karachi Neighborhood Improvement Project

Concrete pouring , section 07 level 1 slab underground parking plaza

Concrete pouring , section 07 level 1 slab underground parking plaza

  • Post author:Admin
  • Post published:September 30, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Concrete pouring , section 07 level 1 slab underground parking plaza
Concrete pouring , section 03 level 1 slab underground parking plaza

Concrete pouring , section 03 level 1 slab underground parking plaza

  • Post author:Admin
  • Post published:September 28, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Concrete pouring , section 03 level 1 slab underground parking plaza
Reinforcement is in final level for concrete pouring , section 07 level 1 slab underground parking plaza

Reinforcement is in final level for concrete pouring , section 07 level 1 slab underground parking plaza

  • Post author:Admin
  • Post published:September 27, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Reinforcement is in final level for concrete pouring , section 07 level 1 slab underground parking plaza
Utilities shifting ( partial portion) due to sewer line and storm water drain alignment is underway

Utilities shifting ( partial portion) due to sewer line and storm water drain alignment is underway

  • Post author:Admin
  • Post published:September 25, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Utilities shifting ( partial portion) due to sewer line and storm water drain alignment is underway
Epoxy base paint work and MEP works ( Electrical Cable trays , Fire suppression system and under other conduit works) are underway at underground parking plaza

Epoxy base paint work and MEP works ( Electrical Cable trays , Fire suppression system and under other conduit works) are underway at underground parking plaza

  • Post author:Admin
  • Post published:September 24, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Epoxy base paint work and MEP works ( Electrical Cable trays , Fire suppression system and under other conduit works) are underway at underground parking plaza
Concrete of section 03 (partial) is poured and reinforcement of section 07 ( partial) is under preparation

Concrete of section 03 (partial) is poured and reinforcement of section 07 ( partial) is under preparation

  • Post author:Admin
  • Post published:September 23, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Concrete of section 03 (partial) is poured and reinforcement of section 07 ( partial) is under preparation
Stone Soling and Lean Concrete base is under way at section 08 underground parking plaza

Stone Soling and Lean Concrete base is under way at section 08 underground parking plaza

  • Post author:Admin
  • Post published:September 21, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Stone Soling and Lean Concrete base is under way at section 08 underground parking plaza
Scaffolding for water tank Slab preparation is under way at underground parking plaza

Scaffolding for water tank Slab preparation is under way at underground parking plaza

  • Post author:Admin
  • Post published:September 20, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Scaffolding for water tank Slab preparation is under way at underground parking plaza
Subbase preparation is underway at Deen M Wafai Road

Subbase preparation is underway at Deen M Wafai Road

  • Post author:Admin
  • Post published:September 19, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Subbase preparation is underway at Deen M Wafai Road
Stone ballast layer compaction is in process at Deen Mohammad Wafai Road ( 100-meter Stretch)

Stone ballast layer compaction is in process at Deen Mohammad Wafai Road ( 100-meter Stretch)

  • Post author:Admin
  • Post published:September 18, 2019
  • Post category:Progress Updates
  • Post comments:0 Comments

Continue Reading Stone ballast layer compaction is in process at Deen Mohammad Wafai Road ( 100-meter Stretch)
  • 1
  • 2
  • 3
  • Go to the next page

Recent Posts

  • Inauguration Ceremony of Rehabilitation and Reconstruction of Fishermen Chowrangi and Road 9000 in Korangi.
  • Inauguration Ceremony of Rehabilitation and Reconstruction of Fishermen Chowrangi and Road 9000 in Korangi.
  • 4.9 km long road has been completed under the sub-project
  • Fishermen Chowrangi in Korangi
  • Inauguration Ceremony of Fishermen Chowrangi

Recent Comments

    Archives

    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • August 2020
    • April 2020
    • March 2020
    • February 2020
    • December 2019
    • November 2019
    • October 2019
    • September 2019
    • August 2019
    • July 2019
    • June 2019
    • May 2019
    • April 2019
    • March 2019
    • February 2019
    • January 2019
    • December 2018
    • September 2018

    Categories

    • Progress Updates
    • Uncategorized

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org

    Copyright 2020 - Karachi Neighborhood Improvement Project


    Notice: ob_end_flush(): failed to send buffer of zlib output compression (1) in /home/knipgos/domains/knip.gos.pk/public_html/wp-includes/functions.php on line 4673

    Notice: ob_end_flush(): failed to send buffer of zlib output compression (1) in /home/knipgos/domains/knip.gos.pk/public_html/wp-includes/functions.php on line 4673